CTrain Station Platform Construction Schedule

Calgary Transit is preparing for the operation of four-car CTrains.  To achieve this, most of the older CTrain station platforms require work to extend them to accommodate four-car trains.

Work to upgrade the stations will be conducted with limited disruption to train service, and Calgary Transit will make every effort to ensure customer inconvenience is kept to a minimum.

However, to safely carry out some work, it may be necessary to have weekend closures. Below is a tentative schedule of the stations requiring construction, including their anticipated start dates and if they will require an extended station closure.

PLEASE NOTE: EXPECTED DATES ARE APPROXIMATE AND MAY CHANGE

Last updated: April 11, 2014

BARLOW/MAX BELL Started January, 2014. Work expected to be completed Summer - Fall, 2014. More info: Calgary.ca/4carplatforms
BRIDGELAND/MEMORIAL Started February, 2014. Work expected to be completed Summer - Fall, 2014. More info: Calgary.ca/4carplatforms
ZOO Started March, 2014. Work expected to be completed Fall - Winter, 2014.
More info: Calgary.ca/4carplatforms
39 AVENUE Started April, 2014. Work expected to be completed Fall, 2014.
SAIT Expected to start in Summer, 2014 for approximately 6 months.
BANFF TRAIL Expected to start in Summer, 2014 for approximately 6 months.