|
CTrain Station Platform Construction Schedule
In response to customer demand, Calgary Transit is preparing to operate four-car CTrains by 2014. In order to do so, all CTrain station platforms must be able to accommodate four-car trains, which will require extensions to most of the older stations.
The work to upgrade the stations will be done with limited disruption to train service, and we will make every effort to ensure customer inconvenience is kept to a minimum.
However, to safely conduct some work, it may be necessary to have weekend closures. In a couple of cases, due to the nature of the station and the work required, a longer station closure will be required.
Below is a tentative schedule of the stations requiring construction, including their anticipated start dates and if they will require an extended station closure.
PLEASE NOTE: EXPECTED START DATES ARE APPROXIMATE AND MAY CHANGE
Last updated: March 25, 2013
|
CHINOOK |
Started July 16, 2012. Station closure started January 14, 2013 |
|
RUNDLE |
Construction started in January 2013; station closure May long weekend 2013; complete fall 2013 |
|
MARLBOROUGH |
Construction starts mid-March 2013; possible station closure - August long weekend 2013; complete late fall 2013 |
| FRANKLIN |
Construction expected to start mid-April 2013; possible station closure – Thanksgiving long weekend 2013; complete late fall 2013 |
|
ANDERSON |
Expected to start June, 2013 |
|
LIONS PARK |
Expected to start June, 2013 |
|
UNIVERSITY |
Expected to start June, 2013 |
|
VICTORIA PARK/STAMPEDE |
Expected to start July, 2013 |
|
39 AVENUE |
Expected to start in 2013 or 2014 |
|
BARLOW/MAX BELL |
Expected to start in 2014 |
|
BRIDGELAND/MEMORIAL |
Expected to start in 2014 |
|
ZOO |
Expected to start in 2014 |
|
SAIT |
Expected to start in 2014 |
|
BANFF TRAIL |
Expected to start in 2014 |
|